Project Info
- Rabigh Project Site 01 : Independent Power Plant 2 @ Al-Mourjan
- Client : Saudi Electricity/Acwa Power
- Main Contractor : Samsung C & T
- Status : Completed and Handed Over
Project Details
6 Km Asphalted Entrance Road to main gate including Lighting Pole and boundary fence works
Administration Building (ABx1)
Central Control Room Building (CCRx1)
Sea-Water Intake Building (SWIx1)
Electrical Control Buildings 01 to 06 (x6 Buildings)
Workshop and Warehouse Buildings (x1)
More Project Details
Scope of Work: Main Access Road including Electrical Works, HCIS Fences, Underground concrete works, Architectural/Building Works including all finishing and all MEP works of following;
- 6 Km Asphalted Entrance Road to main gate including Lighting Pole and boundary fence works
- Administration Building (ABx1)
- Central Control Room Building (CCRx1)
- Sea-Water Intake Building (SWIx1)
- Electrical Control Buildings 01 to 06 (x6 Buildings)
- Workshop and Warehouse Buildings (x1)