Rabigh Project Site 01: Independent Power Plant 2 @ Al-Mourjan

Project Info
  • Rabigh Project Site 01 : Independent Power Plant 2 @ Al-Mourjan
  • Client : Saudi Electricity/Acwa Power
  • Main Contractor : Samsung C & T
  • Status : Completed and Handed Over
Project Details

6 Km Asphalted Entrance Road to main gate including Lighting Pole and boundary fence works
Administration Building (ABx1)
Central Control Room Building (CCRx1)
Sea-Water Intake Building (SWIx1)
Electrical Control Buildings 01 to 06 (x6 Buildings)
Workshop and Warehouse Buildings (x1)

More Project Details

 

Scope of Work: Main Access Road including Electrical Works, HCIS Fences, Underground concrete works, Architectural/Building Works including all finishing and all MEP works of following;

  • 6 Km Asphalted Entrance Road to main gate including Lighting Pole and boundary fence works
  • Administration Building (ABx1)
  • Central Control Room Building (CCRx1)
  • Sea-Water Intake Building (SWIx1)
  • Electrical Control Buildings 01 to 06 (x6 Buildings)
  • Workshop and Warehouse Buildings (x1)