Petrofac (Civil,Tanks, SS and Road works)

Project Info
  • Client : Saudi Aramco/Sumitomo Chemicals
  • Rabigh Project Site 02 : Common Utilities/Tank Farm Pkgs@ PetroRabigh
  • Main Contractor : Petrofac
  • Status : UO2/UO3 Pkg's Handed Over & UO4 Pkg Ongoing (Progress 87.3% as of 4th August)
Project Details

Earthworks and Under/Above Ground Civil Works

More Project Details

Scope of Work: Earthworks and Under/Above Ground Civil Works as follow;

  • Site Preparation & Temporary Facilities including HCIS Fences
  • Waste & Sewage Water Plant Complete Package including coating/painting
  • SS Buildings include all finishes and plumbing works x 3 (Pre-cast+Cip)
  • Tanks foundations including Dyke Walls/Ditches/HDPE/Marl Paving x 5
  • Pipe Sleepers and different kind of supports/foundations
  • Underground Pipe & Cable Trenches including SYS/RTR pipe laying 2” to 24”
  • Asphalt Roads, Markings & Concrete Paving’s